EXPERIENCE 1
Company Name – DAR-ENGINEERING
Oct. 2011 To date
Project-1
E & DD DESIGN REVIEW TEAM SAUDI ELECTRICITY COMPANY-COA, KSA (from Oct.2011 – Oct. 2012)
Position- Electrical Engineer
Duties and Responsibilities:
• Responsible to review & approvals of base design & details design drawings, materials, calculations & specification pertaining to 132kV, 110Kv, 33kV, 13.8kV & low voltage substations submittals by various contractors. Prequalification approvals for the materials as per standards & specifications under E &DD department of Saudi Electricity Company.
Project- 2
JEDDAH SOUTH POWER PLANT 380KV GIS SUBSTATIONS, FOR SAUDI ELECTRICITY COMPANY-WOA, KSA (from Nov 2012 to July 2013)
Position- Project Engineer
Duties and Responsibilities:
• Responsible for Project Management, Coordination, Monitoring Scheduling and Contract Compliance along with Installation, for Power Plant 380kV Substation
Project-3
SHUQAIQ POWER PLANT 380KV GIS SUBSTATIONS, FOR SAUDI ELECTRICITY COMPANY-WOA, KSA (from Aug 2013 to April 2014)
Position- Project Engineer
Duties and Responsibilities:
• Responsible for Project Management, Coordination, Monitoring Scheduling and Contract Compliance along with Installation, for Power Plant 380kV Substation
Project-4
STATIC VAR COMPENSATION FOR HARMAIN HIGH SPEED RAILWAY (SVC), FOR SAUDI ELECTRICITY COMPANY-WOA, KSA (from April 2014 to June 2017)
Position- Project Engineer
Duties and Responsibilities:
• Project Management along with Installation, Coordination, Monitoring, Schedule and Contract Compliance including Testing & commissioning of all entire substations along with SAS system for Harmain High Speed Railway 380kV GIS for both the substations at Makah & Madinah (HHR-1 & 6)
Project-5
380/110/13.8kV HUNAYN (MAKKAH) BSP (SAUDI ELECTRICITY COMPANY-WOA) KSA (from May 2015 to Oct. 2019)
Position- Project Engineer
Duties and Responsibilities:
• Responsible for Consulting the Substation Project Management along with Installation, Coordination, Monitoring, Schedule and Contract Compliance including Testing & commissioning of all entire substations along with SCADA & SAS system.
Project-6
HOSNA LONG TERM CARE, RIYADH, KSA, (Nov.2019 To Dec. 2021)
Position- Sr. Electrical Engineer
Duties and Responsibilities:
• Responsible for Project Management along with Installation, of all electrical system, low current, Electronic safety & security system, BMS, Hospital equipment & Fire alarm etc.
Along with Medium Voltage Switchgear, 6 nos. of 2MVA Transformers, RMU, UPS & ATS with 4 Nos. of Generators set for emergency supply.
Project-7
115/33/13.8kV SUBSTATIONS (SAUDI ELECTRICITY COMPANY-EOA) KSA (from 11 Dec. 2021 to Feb. 2022)
Position- Sr. Electrical Engineer Substation
Duties and Responsibilities:
• Responsible for Project Management, Coordination, supervision of Installation all Materials for all new & expansion substations for SEC EASTERN REGION.
EXPERIENCE 2
Company Name – ARTI INFRA PROJECTS PVT. LIMITED
Sep.2010 – Jan. 2011
Position- Project Manager
Project- MAHARASHTRA STATE ELECTRICITY GAWTHAN PROJECT (PHASEIII) FOR SEPARATION OF AGREECULTURE LOAD FROM VILLAGES, INDIA
Duties and Responsibilities:
• Installation, Commissioning, Management and Planning for Execution of High voltage Transmission line 132kV up to 62kM, Execution of 20, 5 & 2 MVA, 33/11kV Substations, totals 3 nos.
• Execution of 33/11 kV feeder bay, total 5 nos., 11kv line up to 400 km, Transformer installation for existing S/S (63 KVA to 500 KVA), Low Voltage Line (LT) up to 200 KM) Separation of AG feeder from Gawthan, underground cable whenever NH and railway crossing (3 C95, 240 sq. mm) and Communication and billing with client.
EXPERIENCE 3
Company Name – STERLING & WILSON LIMITED
Sep.2010 – Jan. 2011
Position- Project Manager
Project- MAHARASHTRA STATE ELECTRICITY GAWTHAN PROJECT (PHASEIII) FOR SEPARATION OF AGREECULTURE LOAD FROM VILLAGES, INDIA
Duties and Responsibilities:
• Installation, Commissioning, Management and Planning for Execution of High voltage Transmission line 132kV up to 62kM, Execution of 20, 5 & 2 MVA, 33/11kV Substations, totals 3 nos.
• Execution of 33/11 kV feeder bay, total 5 nos., 11kv line up to 400 km, Transformer installation for existing S/S (63 KVA to 500 KVA), Low Voltage Line (LT) up to 200 KM) Separation of AG feeder from Gawthan, underground cable whenever NH and railway crossing (3 C95, 240 sq. mm) and Communication and billing with client.
EXPERIENCE 4
Company Name – FRIGERIO CONSERVA ALLANA LIMITED
Oct.2009 – Aug. 2010
Position- Sr. Electrical Engineer
Project- INDUSTRIAL AUTOMATION FOR FOOD PRCESSING AND COLD STORAGE, INDIA
Duties and Responsibilities:
• Installing, Commissioning and Testing of Six DG sets each having capacity of 1010 KVA and Two 33 KV/415 V, 3 MVA Substations with PLC control and SCADA System, distribution and scheduling of electrical power according to load schedule from DG sets and Substations to various processing plants at FCAL which has different food processing units. Installing.
• Commissioning & Testing of PLC based Control System of various equipment like Compressors, Accumulators, Ammonia pumps, Oil Pumps, Condensers, ACUs, AHUs, and different temperature maintained refrigeration plants like Chiller rooms, Cold Storage, Frozen packing and Plate freezer etc.
• Power distribution and control of various drives and equipment of Rendering and crushing plant and Boiler.
EXPERIENCE 5
Company Name – R F ARRAYS LIMITED
Jan.2009 – Sep. 2009
Position- Business Development Executive
Project- WIRELESS SUBSTATIONS & LIGHTINGS MONITORING & CONTROL BY ZIG-BEE TECHNOLOGY
Duties and Responsibilities:
• Worked as a Sr. Executive Business Development on centralized wireless Substation monitoring & Control systems using Zig-Bee and GSM technology for various Substations at ISRO, BEST and APSEB.
• Worked on wireless lighting and AMR Systems for CGL and Western Railways etc. Settled and facilitated the implementation of the company’s Business, Business Development Support- tools and systems to support quality relationship.
• Timely received customer feedback and did regular follow-up’s took responsibility of production activities on as and when required basis. Building Management Systems, designing, making drawings for new building and its protection including ACs, CCTV, DG sets etc.
EXPERIENCE 6
Company Name – LARSON & TOUBRO LIMITED
Aug.2006 – Dec. 2008
Position- Overall in charge
Project – 1 MAINTENANCE & SERVICES, Tata Motors, India, 2006 - 2007
Duties and Responsibilities:
• Provided pure & unbreakable electric supply to all workshops at car plant of TML and substations in TML. Attended all electric as well as tripping complaint whenever occurred in shops &substation and rectified within short period. Maintained and operated Ring Main Feeder Systems etc.
Position- Site in charge,
Project – 2 Hindustan Petroleum Switchgears, Mumbai, India 2007 - 2008
Duties and Responsibilities:
• Worked as a Site in charge for erecting, commissioning and testing of LT switchgears and different drive panels at Hindustan Petroleum Corporation Ltd.(HPCL) for their GFIC Projects
EXPERIENCE 7
Company Name – ABB LIMITED
Oct.2003 – Jul. 2006
Position- Project Engineer
Project- 1 440/110/33 kV Bihar Sharif Substation (PGCIL), Vadodara, India from 2003 to 2004
Duties and Responsibilities:
• Project Management along with Installation, Coordination, Monitoring, Schedule and Contract Compliance including Testing & commissioning of all entire substation for Power Grid Corporation India Limited.
Position- Project Engineer
Project- 2 132/33 kV Baramkela Substation (CSEB) from 2004 to 2006
Duties and Responsibilities:
• Project Management & Site Management along with Installation, Coordination, Monitoring Schedule and Contract Compliance including Testing & commissioning of all entire substation for Chhattisgarh Electricity Board Baramkela
EXPERIENCE 8
Company Name – CTR LIMITED
May.2003 Sep. 2003
Position- Service Engineer (Overall India)
Project- Nitrogen Transformer Fire Fighting System,
Duties and Responsibilities:
• Servicing, Testing & commissioning of Nitrogen Injection Fire fighting for high voltage transformers above 100MVA.Worked in all over India.